DIN 276 is a DIN standard used in architectural engineering for two main services:

Scope

Only part 1 building construction (last updated 2008–12) and part 4 engineering are valid.[1]

"This part of the standard applies to cost planning in building construction, in particular for the determination and organization of costs. It covers the costs of new construction, reconstruction and modernization of buildings and related project-related costs; for building construction costs , DIN 18960 applies.[2]"

With the new edition of DIN 276-1 of December 2008, amendment A1 of February 2008 and amendment 1 of February 2007 were incorporated into the standard.[3]

The version of April 1981 of DIN 276 is used in the HOAI 1996/2002 for fee determination. The old version is used, because the federal legislature did not follow the further development of DIN 276 in the price law for architects and engineers and did not adapt the cost groups in the regulation text of the HOAI 1996. The cost calculations are thus to be set up in two structures: in the most recent for project processing and in the version of 1981 only for fee determination.[4]

General changes to the new edition 2006

In 2006, changes were made to the title and structure to open the standard beyond building construction to other areas of construction. Compared with DIN 276: 1993–06, the following changes were made:[5]

Substantive changes

Editorial changes

References

  1. ^ Mittag, Martin (8 March 2013). Ausschreibungshilfe Außenanlagen und Tiefbau. ISBN 9783322802088.
  2. ^ "Project Management for Construction: Cost Estimation". www.cmu.edu. Retrieved 2021-01-09.
  3. ^ Mittag, Martin (8 March 2013). Ausschreibungshilfe Außenanlagen und Tiefbau. ISBN 9783322802088.
  4. ^ "Forensic Medicine MCQs - Identification". Retrieved 2021-01-09.
  5. ^ "quality control project: Topics by Science.gov". www.science.gov. Retrieved 2021-01-09.
  6. ^ "Strategic Management for Competitive Advantage". Harvard Business Review. 1980-07-01. ISSN 0017-8012. Retrieved 2021-01-09.
  7. ^ Cerezo-Narváez, Alberto; Pastor-Fernández, Andrés; Otero-Mateo, Manuel; Ballesteros-Pérez, Pablo (January 2020). "Integration of Cost and Work Breakdown Structures in the Management of Construction Projects". Applied Sciences. 10 (4): 1386. doi:10.3390/app10041386. hdl:10251/193520.