The Mountain Valley Pipeline (MVP) is a natural gas pipeline being constructed from northwestern West Virginia to southern Virginia. The MVP will be 304 miles (489 km) long, and there is also a proposed Southgate Extension which will run 75 miles (121 km) from Virginia into North Carolina.[1] The completed pipeline will have a capacity of 2 million dekatherms (Dts) of natural gas per day (approximately 200 TWh per year), with gas produced from the Marcellus and Utica shale formations.
The pipeline has met with opposition in the form of legal challenges, regulatory hurdles, and direct action. Some of the issues raised by opponents include the seizure of land through eminent domain and negative impacts to the forests, waterways, and protected wildlife. Opponents have also voiced concerns about the project's contribution to climate change, and permits have been denied on the basis of environmental justice laws in the state of Virginia. These challenges have resulted in the project being years behind schedule and billions of dollars over budget.[2][3]
The American Petroleum Institute stated that the pipeline would get a cleaner, cheaper fuel to market and spur the economy.
In July 2022, West Virginia senator Joe Manchin made a deal with US Democratic Party leadership to ease regulatory barriers for the MVP in exchange for his support of the Inflation Reduction Act. His proposed legislation would have required the Federal Energy Regulatory Commission (FERC) to take "all necessary actions" to ensure completion of the MVP.[4] This deal prompted protests in Washington, DC in September, led by Indigenous people and others voicing environmental justice concerns.[5][6] Manchin's bill was later withdrawn.[4]
On June 3, 2023, President Biden signed into law the Fiscal Responsibility Act that requires all federal permits needed to complete the project be issued by June 24, 2023. The project developer expects the pipeline to be in-service by mid-year 2024.[7][8]
The MVP project is a natural gas pipeline from northwestern West Virginia to southern Virginia retrieving its supply from the Marcellus and Utica shale sites. It is expected to provide two billion cubic feet of firm capacity per day.[9] The pipeline is projected to span approximately 303 miles (488 km),[10] and its route crosses the Appalachian Trail near Peters Mountain Wilderness in Virginia.[11]
The MVP is owned by Mountain Valley Pipeline, LLC (MVP LLC), which is a joint venture between Equitrans Midstream, NextEra Energy Resources, Con Edison Transmission and other midstream partners.[12][13] The MVP would be operated by Equitrans Midstream which is the majority owner. Equitrans Midstream was formed in a June 2020 merger.[14]
The MVP is an interstate pipeline so it is federally regulated by the Federal Energy Regulatory Commission under United States Natural Gas Act.[10][15] State level ordinances also apply. In October 2015, MVP LLC applied for permits for the pipeline from FERC, and the regulatory commission issued the Final Environmental Impact Statement in June 2017.[16] The pipeline's operation would be regulated by the Pipeline and Hazardous Materials Safety Administration (PHMSA).[17]
The evidence of a market demand and Federal Energy Regulatory Commission (FERC) Certificate policy requires at least 25 percent of the Mountain Valley Pipeline's capacity to deliver natural gas be met by service contract agreements in order to justify the need for the project.[18] MVP LLC was able to secure these service contracts allowing them to proceed with the proposed project. The completed pipeline would have the ability to ship 2 million dekatherms (Dts) of natural gas per day for distribution, with a large quantity of that gas being produced from the Marcellus and Utica shale formations.[12]
Opposition was met during the initial request to obtain a certificate of convenience and necessity from the FERC.[18] Some of the issues raised by citizen groups include the right of eminent domain and the potential for negative impacts to the forests, waterways, and protected wildlife during construction.[19][20] Concerns were raised because the route cuts across the Appalachian Trail.[11] Activists have set up numerous blockades to prevent construction along the pipeline path including a month-long tree-sit near Peters Mountain,[21][22] an aerial blockade in which a woman occupied a platform atop a pole for 57 days,[23] other aerial blockades, and the 932 day yellow finch tree-sit from September 2018 to March 2021.[24][25] Protestors have also blocked construction by parking junk cars on the pipeline route or locking themselves to machinery;[26] in one case, a professor chained herself to construction equipment.[27][28] Obstruction of pipeline construction has been ongoing in spite of significant criminal and civil penalties being levied against protestors.[25][26]
The head of the Jefferson National Forest was reassigned, allegedly due to heavy handed tactics involving the protest, which included running ATVs on a section of the Appalachian Trail,[29] and, according to Outside magazine, blocking food and water supplies to protesters.[30] In Virginia, bumper stickers are appearing on cars that read "No Pipeline". Many articles against the pipeline have been published in The Roanoke Times, and many protests have been organized.[31][32][33][34]
The MVP has been cited by government agencies for violations of Virginia's Stormwater Management Act because of problems with runoff from land clearing while installing the pipeline.[35] The pipeline was challenged in court, including lawsuits during 2018 in which cultural preservation officers from the Rosebud Sioux Tribe and the Cheyenne River Sioux Tribe sued FERC for failing to satisfy the requirements of the National Historic Preservation Act after they found evidence of burial mounds along the path of the pipeline. These lawsuits were thrown out by federal courts in February 2019.[36]
Many landowners complain that they are kept up at night by construction, mainly because most of the land used to build the pipeline was taken from private landowners by eminent domain. A ruling by U.S. District Court Judge Elizabeth Dillon on January 31, 2018, granted the right of eminent domain to MVP LLC in a disputed area but required current appraisals and bonds be set forth to compensate for any losses incurred by the land owners.[37]
Landowners located along the pipeline project see the privately owned pipeline as a "government sanctioned land grab" impacting not only the environment, but also the local economies of surrounding towns.[38] In June 2018, a federal court put a hold on a required permit for construction of the pipeline in Monroe County, West Virginia.[39]
Compressor stations that were proposed as part of the Southgate extension were denied permits in Virginia in 2021 when state regulators ruled that the permits would violate state environmental justice laws. Residents were concerned about noise, pollution, and the danger of explosions.[40]
The American Petroleum Institute stated that the pipeline would get a cleaner, cheaper fuel to market and spur the economy.[41] There are concerns however from communities that will be impacted by the pipeline's construction and from groups who want to preserve historical landmarks, forests, wildlife, waterways, and parks. Questions were raised regarding the need for the project and its purpose. Additional inquiries called in to question whether there were alternatives to avoid impacts to the forest among other things which were detailed in the Final Environmental Impact Statement, along with recommendations by the FERC to minimize the impacts on the environment.[42][18]
The environmental concerns of the pipeline include threats to the streams, rivers, and drinking water along the route. This can include the forests, endangered species, fish nurseries, and the public lands that surround the pipeline.[43] Water contamination has been one of the biggest concerns with the growth of this project, and there are concerns by some about the path of the pipeline, which cuts across sections of national forests including the Jefferson National Forest in Virginia and West Virginia along with the Appalachian Trail.
The Appalachian Trail Conservancy has opposed the pipeline,[44] with the following concerns:
The Natural Resources Defense Council, an environmental advocacy group, says:
October 2014
October 23, 2015
October 13, 2017
December 2017
December 20, 2017
December 22, 2017
January 31, 2018
2018 (first quarter)
July 3, 2018
July 27, 2018
October 2, 2018
November 27, 2018
December 2018
March 1, 2019
October 11, 2019
October 15, 2019
June 2020
July 31, 2020
August 11, 2020
August 25, 2020
September 4, 2020
September 11, 2020
September 22, 2020
October 9, 2020
February 21, 2022
July 27, 2022
September 8, 2022
May 31, 2023
June 1, 2023
July 9, 2023
July 10, 2023
July 24, 2023
July 27, 2023
August 8, 2023