Snowy 2.0 Pumped Storage Power Station
Map
CountryAustralia
LocationSnowy Mountains
Coordinates35°47′S 148°27′E / 35.78°S 148.45°E / -35.78; 148.45
StatusUnder construction
Construction began2019; 5 years ago (2019)
Construction costAUD 12 billion[1]
Owner(s)Snowy Hydro
External links
Websitehttps://www.snowyhydro.com.au/

Snowy 2.0 Pumped Storage Power Station or Snowy Hydro 2.0 is a pumped-hydro battery megaproject in New South Wales, Australia. The dispatchable generation project expands upon the original Snowy Mountains Scheme(ex post facto Snowy 1.0) connecting two existing dams through a 27-kilometre (17 mi) underground tunnel and a new, underground pumped-hydro power station.[2] Construction began in 2019.[2] It is expected to supply 2.2 gigawatts of capacity and about 350,000 megawatt hours of large-scale storage to the national electricity market.[3][4] It is the largest renewable energy project under construction in Australia.[5] It includes one of the largest and deepest cavern excavations ever undertaken.[6]

It is designed for grid stabilization; to be a backup at times of peak demand and for when solar and wind energy are not providing power.[7] Snowy Hydro acts like a giant battery by absorbing, storing, and dispatching energy.[3] The battery is designed to operate for up to 175 hours of temporary supply.[8] It is Australia's largest energy project,[9] estimated to cost 12 billion Australian dollars. By 2023, AU$4.3 billion had been spent.[1] The project is led by public company Snowy Hydro Limited.[9] When complete it is expected to have a large impact on the price and reliability of electric power.[10]

History

Initial plans for a power station at the location were discussed in 1966.[11] Further studies were undertaken in 1980 and 1990.[11] The current project originated as the centrepiece of Malcolm Turnbull's climate change policy in 2017.[12] A feasibility study carried out in 2017 finding the project was both technically and financially feasible.[11] The study was released on 21 December 2017 and found the project cost would be between $3.8 and 4.5 billion.[13]

The first tunnel that was completed by October 2022, was a 2.85 kilometre section that provided main access at Lobs Hole.[14] It was 10 metres in diameter and provides pedestrian and vehicle access into the power station.[14] By May 2023 the emergency, cable and ventilation tunnel was excavated.[15] It is 2.93 kilometre long, 10 metres in diameter and will be used for power station ventilation and high-voltage cables.[15] Excavation of the transformer and machines halls began in June 2023.[6]

It was originally expected to be completed by 2024.[16][17] Snowy Hydro 2.0 has been beset by delays and cost blowouts.[12][7][4] Delays have been caused by the COVID-19 pandemic, global supply chain disruptions, complex design elements and variable site and geological conditions.[8] The delays have raised concerns that Snowy Hydro will not be ready in time for new solar and wind projects coming online as five coal-fired power stations close.[7] AEMO warns that supply gaps will emerge from 2025.[4] The project is currently expected to be fully operational by the end of 2028 and generating power as early as late 2027.[5]

The project is using three tunnel boring machines to dig tunnels.[12] One of the machines, called Florence was stuck for 19 months after encountering soft rock near Tantangara.[17] Florence launched in March 2022. Eight weeks later the machine was bogged in wet soft ground. The machine is capable of digging 30 to 50 metres a day. In December 2022, a sinkhole opened up above the tunnel.[17]

Design and location

It is located remotely within the Kosciuszko National Park in the Snowy Mountains.[3] Snowy Hydro 2.0 will use water from the Talbingo Reservoir (bottom storage) and Tantangara Reservoir (top storage).[10] The new power station is being built by the Italian firm Webuild.[18] It will be located in a cavern 800 metres underground.[10] The underground location allows for reduced environmental impacts within the national park. The operational footprint of the facility is less than 0.01% of the total size of the park.[19]

The power station will measure 22 metres (m) wide, 50 m high and 250 m long.[9] The station will house six reversible Francis pump-turbine and motor-generator units.[16] Three units will be of variable speed with the remaining of synchronous speed. Each turbine will have a rated output of 333 megawatts.[20] Power generating equipment is being supplied by Voith.[20]

It will be connected to the grid via the HumeLink transmission line.[12][21] The construction of overhead power lines by TransGrid has been opposed by community advocacy groups.[22] Landholders desire to see the transmission line built underground have been opposed due to prohibitive costs.[22]

See also

References

  1. ^ a b Vorrath, Sophie (31 August 2023). "Bowen confirms $12bn Snowy 2.0 cost blowout, says pitfalls should have been known". RenewEconomy.
  2. ^ a b "History". Snowy Hydro. Retrieved 5 May 2023.
  3. ^ a b c "The next generation of hydropower in Australia". SMEC. 15 October 2022. Retrieved 5 May 2023.
  4. ^ a b c Morton, Adam; Rose, Tamsin; Hannam, Peter (3 May 2023). "Snowy Hydro 2.0 project hit by delay of up to two years and another cost blowout". The Guardian. Retrieved 5 May 2023.
  5. ^ a b Lowrey, Tom (31 August 2023). "Snowy Hydro expansion hits reset button as costs blow out to $12 billion". ABC News. Retrieved 24 October 2023.
  6. ^ a b Cook, Kody (9 January 2024). "Milestone for Snowy 2.0". Utility Magazine. Monkey Media. Retrieved 12 January 2024.
  7. ^ a b c Toscano, Nick; Foley, Mike (3 May 2023). "Snowy 2.0 pumped hydro project hit with new delays, cost blowouts". The Sydney Morning Herald. Retrieved 5 May 2023.
  8. ^ a b "Timeline, budget reset for Snowy 2.0 pumped storage". Hydro Review. 5 April 2023. Retrieved 5 May 2023.
  9. ^ a b c "Snowy 2.0: A pumped-storage plant of colossal proportions". Tractebel. 20 July 2022. Retrieved 5 May 2023.
  10. ^ a b c Ziffer, Daniel (6 January 2023). "Snowy Hydro could change our electricity grid and bring cheap power. But we have to build it". ABC News. Australian Broadcasting Corporation. Retrieved 5 May 2023.
  11. ^ a b c Cella, Lauren (24 January 2020). "Snowy 2.0 underway". Pump Industry. Retrieved 5 May 2023.
  12. ^ a b c d Dhanji, Krishani (3 May 2023). "Snowy Hydro 2.0 pumped-hydro battery project faces a further two years of delays". ABC News. Australian Broadcasting Corporation. Retrieved 5 May 2023.
  13. ^ "Snowy 2.0 feasibility study released". ARENA. 20 December 2017. Retrieved 5 May 2023.
  14. ^ a b "Milestone first tunnel completed for Snowy 2.0". Snowy Hydro. 11 October 2022. Retrieved 5 May 2023.
  15. ^ a b Eastaway, Gail (26 May 2023). "Tunnel vision turns to reality in Snowy Hydro 2.0 milestone". Riotact. Retrieved 26 May 2023.
  16. ^ a b "Snowy 2.0 Hydropower Project, New South Wales". PowerTechnology. Verdict Media. Retrieved 5 May 2023.
  17. ^ a b c Grigg, Angus; Robinson, Lesley; Gock, Kamin. "A sinkhole, toxic gas and the $2 billion mistake behind Snowy 2.0's blowout". ABC News. Retrieved 23 October 2023.
  18. ^ "Snowy 2.0 : Webuild Group". Webuild. Retrieved 24 October 2023.
  19. ^ "FAQs". Snowy Hydro. Retrieved 5 May 2023.
  20. ^ a b "Voith Snowy 2.0". ICN Gateway. Retrieved 5 May 2023.
  21. ^ "HumeLink inches ahead as state inquiry rules out putting lines underground". RenewEconomy. 31 August 2023.
  22. ^ a b Burke, Conor (31 August 2023). "Inquiry deems Transgrid's HumeLink energy transmission project will remain above ground". ABC News. Retrieved 25 October 2023.