Capital Line
Capital Line crossing the North Saskatchewan River
Overview
LocaleEdmonton
Termini
Stations15
Service
TypeLight rail
SystemEdmonton Light Rail Transit
Operator(s)Edmonton Transit Service
Depot(s)D.L. MacDonald Yard
History
OpenedApril 22, 1978
Technical
Line length21 km (13.0 mi)
Number of tracks2
CharacterSurface line outside of city centre, subway style line under downtown and the UofA.
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Operating speed80 kilometres per hour (50 mph) maximum[1]
Route map
CN Lines
Clareview
Clareview Transit CentreParking
137 Avenue
Belvedere
Belvedere Transit CentreParking
CN Lines
Coliseum
Coliseum Transit Centre
CN Spur End
Stadium
Stadium Transit CentreParking
Churchill
Metro Line Valley Line
Valley Line to
102 Street and Mill Woods
Central
Metro Line
Bay/Enterprise Square
Metro Line
Corona
Metro Line
Government Centre
Government Centre Transit Centre Metro Line
University
University Transit Centre Metro Line
Health Sciences/Jubilee
Metro Line
McKernan/Belgravia
South Campus/
Fort Edmonton Park
South Campus/Fort Edmonton Park Transit Centre
Southgate
Southgate Transit Centre
Century Park
Century Park Transit Centre

Handicapped/disabled access All stations are accessible

The Edmonton LRT Capital Line is a light rail transit line running from northeast Edmonton to the south. Operated by the Edmonton Transit Service, the line provides access to Downtown Edmonton and the University of Alberta. The Capital Line currently consists of fifteen stations, six of which are underground. Seven stations are shared with the Metro Line.

History

This section needs additional citations for verification. Please help improve this article by adding citations to reliable sources in this section. Unsourced material may be challenged and removed. (October 2013) (Learn how and when to remove this template message)

On April 22, 1978, the line opened between Belvedere and Central stations. At the time (and for another 37 years) the system consisted solely of the single line. It was not named the Capital Line until 2012 when expansion plans were revealed for additional lines.[2]

The 1980s were a decade of expansion for the Capital Line. It expanded northwards toward Clareview in 1981, and westwards toward Bay and Corona, under the downtown core in 1983. Another underground extension was completed in 1989 with the opening of Grandin, now known as Government Centre.

One station opened in the 1990s, University, in August 1992. The underground station was connected to the downtown leg by the Dudley B. Menzies Bridge.

During the 2000s, under the mayorship of Stephen Mandel, the Capital Line was expanded southward. Health Sciences opened in 2006, the first new station in 14 years. In 2009, McKernan/Belgravia and South Campus opened, followed by Southgate and Century Park in 2010.

After the completion of the south leg of the Capital Line, city council shifted their efforts towards the new Metro Line.

Future

Approved LRT lines and stations

South expansion

In January 2008, Mayor Stephen Mandel announced that the southern leg will be extended further south along 111 Street to Anthony Henday Drive, and then west to 127 Street SW. There will be a station and a 1,100-car Park and Ride between 127 Street and 135 Street at Ellerslie Road. A new LRT maintenance facility will also be built as part of the extension. Eventually, the LRT will continue south for another stop at 41 Avenue SW. City council approved the route to the Ellerslie Station, and for construction to begin on the Park and Ride in July 2009.[3] Construction of the Heritage Valley Park and Ride began in May 2018, and was completed in December 2019.[4] The Transit Centre provides shuttle service to and from Century Park Transit Centre until the Capital Line LRT is extended to Ellerslie Road.[5]

In June 2017, additional preliminary engineering from Century Park to Ellerslie Road was started to review and refresh the 2010 preliminary design, bring the project up to current standards and reflect the principles of Urban LRT. This work was completed in the end of 2018 and looked at the feasibility of adding a station adjacent to Twin Brooks and the potential for crossings to be raised or lowered, from street level, at 9 and 12 Avenues on 111 Street, and at Ellerslie Road. Integration of the stations into the adjacent communities, with respect to aesthetics and materials, was also reviewed.[6] On June 22, 2021, City Council approved the amended plan that includes an elevated station and crossing at Ellerslie Road, and a stop in Twin Brooks.[7]

The 'Capital Line South Phase 1' extension continues to be high floor LRT and is 4.5 km (2.8 mi) long and includes:[8]

In July 2021, the Phase 1 extension was announced as being fully funded with C$ 1 billion in commitments from the city, province, and federal government. The project is expect to begin construction once the Capital Line extension business case has been approved by the Government of Canada's Treasury Board.[9]

In May 2023, due to budget concerns, the plan for an elevated crossing over Ellerslie Road along with an elevated Heritage Valley North Station was changed to an at-grade crossing and an at grade station. A future grade-separated crossing and station will be studied and would be a part of the second extension phase if approved. Other alternatives considered included the deferral of the Twin Brooks station to a future project and changing the material of a sound barrier from wood to concrete, brick or similar materials.[10][11]

In 2022, Phase 1 of the Capital Line extension began early construction works for the underpass at 23 Avenue. The process to select a contractor began in 2022, with the final selection of a contractor expected to take place in late 2023 or early 2024. Major LRT is expected to commence in 2024.[12]

The City of Edmonton is also looking into extending the line even further, now known as 'Capital Line South Phase 2', adding 3 additional stations; Provincial Lands, Heritage Valley and Desrochers. These three stations names, are placeholders and may change once the stations are built. In 2017, the Government of Alberta announced that a new state of the art hospital would be built near the corner of Ellerslie Road and 127 Street SW.[13] There are no specific plans or timeline for an extension to the Edmonton International Airport and Leduc, but an expansion to the airport is the city's long-term goal.[14][15] In late April 2012, the city launched bus route 747 from Century Park Station to the airport.[16]

Northeast expansion

In 2008, Edmonton City Council approved a plan to extend the Capital Line northeast by one station to Gorman Towne Centre.[17] On April 30, 2009, Mayor Stephen Mandel announced a $210 million project to extend the LRT system to a new Gorman Station. The expansion beyond Clareview Station was planned to continue along the CN right-of-way to a station and park-and-ride north of 153 Avenue and Victoria Trail. The plan would have received funding from three levels of government. However, funding was shifted to the Metro Line in July 2009 as city officials saw that line as a higher priority for the city. The city has not ruled out a near-future extension to Gorman.[18] The City completed preliminary engineering on this project in 2010, however there is no budget or timeline for design and construction.[19]

From a land use planning perspective, the City of Edmonton has approved two area structure plans beyond Gorman and Anthony Henday Drive[20] that depict different alignments for further LRT extension into Edmonton's far northeast. Adopted in 2010, the Edmonton Energy and Technology Park Area Structure Plan depicts extension of the LRT along 50 Street across Manning Drive to the north, and then generally paralleling Manning Drive to approximately Highway 28A.[21] This ASP qualifies that this "is a potential alignment only, and will be updated to reflect the completed planning for the Northeast LRT when a final route is determined."[21]

Adopted in 2013, the Horse Hill ASP depicts extension of the LRT along 50 Street to the north, and then northeast along Fort Road to Meridian Street before crossing Manning Drive in a northwesterly direction into the Edmonton Energy and Technology Park.[22] This ASP qualifies that "extension of LRT service will be subject to LRT system planning and design, as well as the availability of funding" and that the alignment it depicts "is preliminary and subject to change."[22]

The Capital Line Northeast is part of the Transportation Master Plan's vision to expand LRT service to all sectors of the city by 2040. Preliminary engineering for an LRT extension north of Clareview station was completed in 2010. The city will move forward to design and construction once funding becomes available.

The preliminary engineering project ends at a future station in the Gorman area, north of 153 Avenue and east of the CN tracks.

The project includes:[23]

Coliseum relocation and additional station

As part of the redevelopment of the Northlands exhibition grounds, plans are in the works to move the current Coliseum station further north and build an additional station to the south of the current Edmonton Expo Centre.[24] More detailed plans and public engagement are scheduled for late 2019.[24]

Stations

Station Grade-Level Transfer Area Opened Location
Clareview Surface Northeast April 26, 1981 53°36′6″N 113°24′41″W / 53.60167°N 113.41139°W / 53.60167; -113.41139 (Clareview)
Belvedere Surface Northeast April 22, 1978 53°35′18″N 113°25′58″W / 53.58833°N 113.43278°W / 53.58833; -113.43278 (Belvedere)
Coliseum Surface Northeast April 22, 1978 53°34′14″N 113°27′30″W / 53.57056°N 113.45833°W / 53.57056; -113.45833 (Coliseum)
Stadium Surface Northeast April 22, 1978 53°33′36″N 113°28′15″W / 53.56000°N 113.47083°W / 53.56000; -113.47083 (Stadium)
Churchill Underground Metro Line Metro Line
Valley Line Valley Line[a]
Downtown April 22, 1978 53°32′39″N 113°29′21″W / 53.54417°N 113.48917°W / 53.54417; -113.48917 (Churchill)
Central Underground Metro Line Metro Line Downtown April 22, 1978 53°32′28″N 113°29′31″W / 53.54111°N 113.49194°W / 53.54111; -113.49194 (Central)
Bay/Enterprise Square Underground Metro Line Metro Line Downtown June 21, 1983 53°32′27″N 113°29′54″W / 53.54083°N 113.49833°W / 53.54083; -113.49833 (Bay/Enterprise Square)
Corona Underground Metro Line Metro Line Downtown June 21, 1983 53°32′27″N 113°30′21″W / 53.54083°N 113.50583°W / 53.54083; -113.50583 (Corona)
Government Centre Underground Metro Line Metro Line Downtown September 1989 53°32′10″N 113°30′37″W / 53.53611°N 113.51028°W / 53.53611; -113.51028 (Grandin)
University Underground Metro Line Metro Line South August 23, 1992 53°31′30″N 113°31′19″W / 53.52500°N 113.52194°W / 53.52500; -113.52194 (University)
Health Sciences/Jubilee Surface Metro Line Metro Line South January 3, 2006 53°31′13″N 113°31′33″W / 53.52028°N 113.52583°W / 53.52028; -113.52583 (Health Sciences/Jubilee)
McKernan/Belgravia Surface South April 26, 2009 53°30′47″N 113°31′34″W / 53.51306°N 113.52611°W / 53.51306; -113.52611 (McKernan/Belgravia)
South Campus/Fort Edmonton Park Surface South April 26, 2009 53°30′10″N 113°31′43″W / 53.50278°N 113.52861°W / 53.50278; -113.52861 (South Campus)
Southgate Surface South April 25, 2010 53°29′8″N 113°31′0″W / 53.48556°N 113.51667°W / 53.48556; -113.51667 (Southgate)
Century Park Surface South April 25, 2010 53°27′27″N 113°30′59″W / 53.45750°N 113.51639°W / 53.45750; -113.51639 (Century Park)

Notes

  1. ^ A surface stop connecting to the Valley Line is located above the underground station.

References

  1. ^ "SD160 Light Rail Vehicle" (PDF). Siemens. Archived from the original (PDF) on 29 September 2012. Retrieved 2 February 2011.
  2. ^ Hoang, Linda (January 31, 2013). "City announces five new LRT line names including 'Energy Line,' 'Capital Line'". CTV News Edmonton. Retrieved June 27, 2016.
  3. ^ "South LRT Extension" (PDF). City of Edmonton. July 2009. Archived from the original (PDF) on 2011-06-16. Retrieved 2010-04-24.
  4. ^ Thompson, Jeremy (August 31, 2020). "$30M Heritage Valley Park-and-Ride complete but unused for 7 months". CTV Edmonton. Retrieved June 23, 2021.
  5. ^ "Capital Line - Heritage Valley Park & Ride". City of Edmonton. Retrieved June 23, 2021.
  6. ^ "Capital Line South - Face Sheet" (PDF). City of Edmonton. September 2018. Retrieved June 23, 2021.
  7. ^ Bartko, Karen (June 22, 2021). "South Edmonton LRT extension approved with elevated station at Ellerslie Road". Global News Edmonton. Retrieved June 23, 2021.
  8. ^ "Capital Line South". City of Edmonton. Archived from the original on September 23, 2020. Retrieved April 28, 2021.
  9. ^ "Capital Line South Extension". Retrieved September 27, 2021.
  10. ^ Boothby, Lauren (May 23, 2023). "Edmonton's Capital Line LRT extension to be scaled back but Twin Brooks station stays". Edmonton Journal. Retrieved June 14, 2023.
  11. ^ City Council - Agenda (June 14,2023)(PDF). City of Edmonton. June 2023. Retrieved June 14, 2023.
  12. ^ "Capital Line - South | City of Edmonton". www.edmonton.ca. Retrieved 2023-06-15.
  13. ^ Ehrkamp, Laura. "New state-of-the-art hospital for south Edmonton". Government of Alberta. Retrieved August 9, 2018.
  14. ^ Johnston, Scott (2017-12-06). "Iveson to make setting aside land for train to airport a priority in 2018". Global News. Retrieved 2021-01-01.
  15. ^ Dion, Andrea (2021-06-22). "Edmonton city council approves $1B LRT expansion project". CTV News. Retrieved 2021-01-01.
  16. ^ "Edmonton International Airport Service". City of Edmonton. Archived from the original on October 7, 2012. Retrieved May 27, 2012.
  17. ^ City of Edmonton - Northeast to Gorman LRT Archived 2012-08-19 at the Wayback Machine
  18. ^ "NAIT LRT line a go after feds approve funding: report". Edmonton Journal. 2009-07-02. Archived from the original on July 5, 2009. Retrieved 2009-09-05.
  19. ^ "Northeast LRT to Gorman". City of Edmonton. Archived from the original on August 19, 2012. Retrieved May 27, 2012.
  20. ^ "Plans in Effect" (PDF). City of Edmonton. May 2013. Archived from the original (PDF) on October 17, 2013. Retrieved October 16, 2013.
  21. ^ a b "Edmonton Energy and Technology Park Area Structure Plan (Office Consolidation)" (PDF) (PDF). City of Edmonton. May 2011. pp. 66–67 (PDF pages 69–70). Archived from the original (PDF) on 2013-10-17. Retrieved October 16, 2013.
  22. ^ a b "Horse Hill Area Structure Plan (Office Consolidation)" (PDF) (PDF). City of Edmonton. July 2013. pp. 34 & 54 (PDF page 38 & 58). Archived from the original (PDF) on October 17, 2013. Retrieved October 16, 2013.
  23. ^ "Capital Line Northeast". City of Edmonton. Retrieved August 9, 2018.
  24. ^ a b Cook, Dustin (23 April 2019). "City moves forward with 'transit villages' plan for Northlands site". Edmonton Journal. Retrieved 23 April 2019.